West wall constructed in two days...north wall (250 linear feet/three floors) in three days...east wall starting now. Masonry already starting on west side while they install panels on the east side. Minimal waste, rapid construction, mold free, ultra-high energy efficiency. If you are not set to turn the corner and utilize WALLY WALLS ULTRAFRAME BUILDING SYSTEM, then I really must know: What are you building with?